Grupo Energía Bogotá and Canada’s La Caisse to Create Brazil’s 5th Largest Power Transmission Platform

19 May 2026 at 00:18

GEB-La Caisse JV to rank among Brazil’s top five power transmitters

Grupo Energía Bogotá (BVC: GEB) and La Caisse, the investment arm of Caisse de dépôt et placement du Québec, have signed a final agreement to merge their respective Brazilian power transmission assets into a single 50/50 jointly controlled platform operating under the name Verene Energia S.A. The transaction was announced May 15, 2026, from Montréal and Bogotá.

The combined entity will consolidate 26 electric transmission concession agreements, more than 9,000 km of transmission lines, and a workforce of over 400 employees across 17 Brazilian states. At that scale, Verene will rank among the five largest power transmission operators in Brazil, a market that has drawn sustained interest from international infrastructure investors as the country advances grid modernization programs.

Verene, which had previously operated as La Caisse’s dedicated transmission platform in Brazil, will continue as the reference vehicle for the combined portfolio. The partners have indicated that the platform will be positioned to pursue acquisitions and network expansions in Brazil’s transmission concession market, with grid modernization and decarbonization cited as the broader policy context driving new investment opportunities.

“By bringing together highly complementary assets under one banner, the partnership establishes Verene as a scaled, business-driven platform with strong financial backing.” — Emmanuel Jaclot, Executive Vice-President and Head of Infrastructure and Sustainability, La Caisse

Grupo Energía Bogotá, headquartered in Bogotá and listed on the Bolsa de Valores de Colombia (BVC: GEB), has operated in Latin America’s energy sector for more than 130 years. The company holds assets in electricity generation, transmission, distribution, and gas transportation and distribution across Colombia, Peru, Brazil, and Guatemala. Its entry into the joint venture contributes its existing Brazilian transmission concessions to the merged platform alongside La Caisse’s Verene assets.

La Caisse manages net assets of 517 billion CAD as of December 31, 2025, on behalf of 48 depositors representing more than six million Quebecers. The fund is active across major financial markets, private equity, infrastructure, real estate, and private credit, and has built a significant infrastructure portfolio in Latin America through investments including the Verene platform.

Juan Ricardo Ortega, president of Grupo Energía Bogotá, described the rationale for the transaction in terms of combining complementary strengths. “By combining our operational expertise and regional market knowledge with the financial strength and global perspective of our partner, we are creating a platform positioned to accelerate growth, expand transmission energy infrastructure, and support Brazil’s energy transition,” he said. “We believe this alliance will generate sustainable value for our stakeholders and contribute to Brazil’s economic and energy development.”

Emmanuel Jaclot, executive vice-president and head of infrastructure and sustainability at La Caisse, framed the deal as a consolidation play. “By bringing together highly complementary assets under one banner, the partnership establishes Verene as a scaled, business-driven platform with strong financial backing,” Jaclot said. “GEB brings more than 130 years of operating heritage and ranks among Latin America’s leading energy infrastructure groups, with deep expertise across the region’s transmission sector. Together, we share a vision to strengthen Verene’s footprint in Brazil through value-creating acquisitions and continued support for the country’s energy transition.”

Financial close is expected by the fourth quarter of 2026, subject to customary closing conditions, regulatory consents, and approvals. BTG Pactual (BVMF: BPAC11) acted as financial advisor to La Caisse, with Pinheiro Neto Advogados serving as legal counsel. Citibank (NYSE: C) advised Grupo Energía Bogotá on the financial side, while Mayer Brown provided legal advice to GEB.

Scatec Commences Construction of 130 MW Barzalosa Solar Project in Colombia

3 April 2026 at 22:18

Renewable expansion strengthens Colombia energy matrix for investors.

The Norwegian renewable energy company Scatec ASA (OSE: SCATC) has reached financial close and initiated construction on the Barzalosa solar power plant in Colombia. The project, located in the municipio of Nariño within the department of Cundinamarca, has a planned capacity of 130 MWp. Total capital expenditure for the facility is estimated at $121 million USD.

The financing structure for the project is based on a 70% leverage model, utilizing a combination of equity and non-recourse debt. Scatec holds a 65% equity stake in the venture, while Norfund, the Norwegian investment fund for developing countries, provides the remaining 35%. The senior debt was provided by Bancolombia S.A. (NYSE: CIB; BVC: BCOLOMBIA) and the Financiera de Desarrollo Nacional (FDN).

The Financiera de Desarrollo Nacional committed a total of 200,358 million COP to the project. This includes a senior debt facility of up to 164,458 million COP with a term of 18 years, representing approximately 50% of the total project debt. Additionally, the FDN provided a bank guarantee of up to 35,900 million COP to substitute reserve accounts for debt service and operation and maintenance costs. The FDN also acted as a co-structurer for the financial framework of the operation.

“The financing of the Barzalosa project reflects the capacity of the FDN to structure long-term financial solutions that make strategic energy transition projects in Colombia viable,” said Enrique Cadena, Vice President of Structured Finance at the FDN.

The law firm Holland & Knight served as legal counsel to the lenders, Bancolombia and FDN, in the COP 330 billion financing transaction. The legal team was led by partner María Juliana Saa, with support from partner Inés Elvira Vesga and associates Juan Sebastián Parra and Juan Felipe Alonso. Other legal and financial advisors involved in the transaction included Cuatrecasas, which advised the borrower; Brigard Urrutia, which advised FDN regarding the credit facility; and Astris Finance, which provided financial structuring advice.

Revenue for the plant will be supported by a 15-year Power Purchase Agreement (PPA) with BTG Pactual Comercializadora de Energía (BVMF: BPAC11). The agreement covers 85% of the estimated energy production and is denominated in Colombian pesos, with adjustments based on the Producer Price Index. The remaining 15% of production will be sold on the Colombian spot market. The project is also eligible for the Cargo por Confiabilidad (reliability charge) and may access resources from the Inter-American Development Bank and the Climate Investment Funds.

Construction includes the installation of the solar array and the development of a six-kilometer transmission line to connect the plant to the national grid. Scatec is acting as the lead developer and the designated Engineering, Procurement, and Construction (EPC) provider, covering approximately 70% of the capital expenditure. The company will also manage operations, maintenance, and asset management. The Barzalosa plant is expected to reach its commercial operation date in the first half of 2027.

❌